4 Replies Latest reply on Aug 21, 2018 9:50 AM by AlasdairRobertson

    When I add a lower or upper bound constraint to a date, the result includes weekends.

    TLuis Rookie

      We use a Weekly HOP for everything which is only M-F.  Is there a way to make it so the weekends are not included?  An example is we don't want a certain Service Request to allow the customer to give a required date within 3 days.  I'm sure there is a long expression that could be written but I'm not understanding why it's not looking at the HOP.  Or perhaps there is a setting somewhere else I need to change?

       

      Thanks

      Teresa